Cable Sizing

Cable Sizing to BS 7671: Which Check Actually Decides the Cable

6 July 2026, updated 9 August 2026

A cable is not sized by BS 7671 — it is sized by ONE of its checks, whichever asks for the most copper, and knowing which one tells you what to change. Work out the smallest conductor each check accepts on its own and the binding constraint falls out, along with how far it pushed the cable past everything else. Plus the two quantities that belong to the path rather than the circuit, which is why a row-by-row calculation misses them.

Read the guide
Containment

Cable Management System Supports: Spacing, Load Path and Fire

8 August 2026

Every cable management system has to be held up, and the spacing table only answers half of it: the On-Site Guide Appendix D spacings meet Chapter 52 and, in the IET's own words, not Regulation 521.10.202. What the clip, conduit and trunking tables say, how the load path changes between clipping direct, a cantilever bracket and a suspended trapeze, and what the fire condition does to each link in it.

Read the guide
Protection

RCD Types Explained: AC, A, F and B — Which Do You Need?

2 August 2026

An RCD only trips on the shapes of residual current it was built to see, and a Type AC sees exactly one of them. What Reg 531.3.3 really says, the topology-to-type table buried in Annex A53, what EV charging actually requires, and why fitting a Type B downstream can blind the older device upstream.

Read the guide
Protection

Do You Need an SPD? Surge Protection Requirements under BS 7671

1 August 2026

Regulation 443.4.1 has two live triggers, not the three most guidance still quotes — and the standard's own figure of about 1000 V per metre of connecting lead means a fully compliant SPD can hand your equipment more voltage than it is rated to withstand. What Section 534 actually requires, and the two different lengths that decide whether any of it works.

Read the guide
Containment

Containment Fill & the 45% Space Factor Explained

3 August 2026

A trunking sized correctly to the 45% rule looks half empty — and 41% of the section is 91% of the permitted fill. Where the limit comes from, why conduit is not sized on a fill percentage at all but on GN1 factors that fall with run length and bends, when the width method replaces both on tray and basket, and how the fill you choose feeds straight back into the cable size through Cg.

Read the guide
Cable Sizing

Maximum Demand & Diversity: What BS 7671 Actually Says

31 July 2026

Regulation 311.1 requires maximum demand to be determined and permits diversity — then publishes no table, no allowances and no method. Where the numbers really come from, how the rules change with the type of building, and why diversity sizes the supply but never the board.

Read the guide
Containment

Cable Cleat Spacing & Short-Circuit Forces

6 July 2026, updated 3 August 2026

BS 7671 requires every conductor to withstand the electromechanical forces of a fault, in four separate places, and gives no method in any of them. The force goes as the square of the PEAK current — so the RMS figure your fault study quotes understates it about five times.

Read the guide
Earthing

Fault Current Division at a Cable Joint Bay

4 August 2026

Inject an earth fault into a joint bay earth grid on a 275 kV route and it leaves two ways — metallically along the ECC, or into the soil. Only the soil part raises the earth potential. How that split is set, why a real route beats the hand calculation, and what actually moves the answer.

Read the guide
Earthing

Earth Potential Rise (EPR) and BS 7671 Section 442

6 July 2026, updated 4 August 2026

What earth potential rise is — and the part most guides leave out. BS 7671 Section 442 says where that rise LANDS in the low voltage installation: on equipment insulation as a stress voltage, or, in exactly one arrangement, on people as a fault voltage.

Read the guide

Have a Project That Needs These Calculations?

We deliver the studies these guides describe — as outsourced, submission-ready packages.

Get in Touch