Containment · Updated 3 August 2026 · For contractors and project engineers
Containment fill is one of the easiest calculations on a project to do and one of the easiest to
misread. The arithmetic is a sum of cable areas against a percentage of a box. The trap is what
that percentage means: a trunking sized correctly to the 45 % rule looks, on the drawing and
on site, as though it is only half used — and the temptation to "use the space that is obviously
there" is exactly what the rule exists to stop.
The short version: enclosed containment is limited to
45 % fill for trunking and 35 % for duct (IET Guidance
Note 1, Appendix A). That limit is not spare room — round cables cannot fill a section
solidly, they have to be installable, and the air is part of the cooling. Conduit is not
sized on a percentage at all: GN1 gives every cable a factor and every conduit size a
factor, and the conduit's factor falls as the run gets longer and gains bends. Open
containment (tray, ladder, basket) is sized on width in a single layer instead,
with no space factor. And whichever you use, the number of circuits you have just bunched together sets
the grouping factor Cg that shrinks every cable's rating.
Try it: the fill explorer
Add cables until the trunking is at its limit, then watch the two percentages diverge. The
"of the whole section" figure is what your eye sees; the "of the permitted fill" figure is what
the standard is asking about. Everything here runs on the same engine as the
containment fill calculator.
This interactive explorer needs JavaScript. Everything it demonstrates is also covered by the
figures and worked numbers below.
Why 45 %, and where the other 55 % goes
The space factor answers a question that has nothing to do with electricity: how much of a box
can cables actually occupy? Three things eat the difference, and none of them is conservatism.
Round cables cannot tile a rectangle. The densest possible packing of identical
circles — a perfect hexagonal stack — still leaves about 9 % air, and that is a theoretical
best with cables that are all the same size and laid deliberately. A mixed bundle pulled into a
trunking on site settles nearer 60 to 70 % of the section at best, and nobody is measuring
it as they go.
Cables have to be installable. A trunking filled to its geometric maximum cannot
be wired. The allowance is what lets cables be laid in and dressed without being forced past each
other, and what lets the next person add a circuit in two years without damaging the insulation
of everything already in there.
The air carries the heat away. Cables in an enclosure warm each other, and the
free space is part of how that heat gets out. This is the same physics as the grouping factor,
which is why filling the containment and derating the cables are two halves of
one decision rather than two separate jobs.
The same trunking read two ways. Twelve 10 mm cables fill 41 % of the section — and 91 % of what the 45 % space factor allows. A trunking that looks half empty is nearly full.
41 % of the section is 91 % full
Take twelve cables of 10 mm overall diameter. Each has a cross-section of
πd²/4 = 78.5 mm², so the twelve need 942 mm². A
50 × 50 mm trunking has roughly 2 300 mm² of usable internal
section, of which 45 % — about 1 037 mm² — may be occupied.
So the cables take 942 of the 1 037 mm² they are allowed: 91 % of the
permitted fill. They also take 942 of the 2 300 mm² that physically
exists: 41 % of the section. Both numbers are correct. Only the first one
is the rule, and a calculator that shows you the second is not telling you that you have room.
Tighten the fill limit and the same cables need a bigger containment. The 45 % is the design rule, not slack left over in the calculation.
Run the same twelve cables against different limits and the point lands: at a notional
100 % they fit a 50 × 50 easily, at 45 % they only just fit it, and at
the 35 % that applies to duct they need the next size up. The limit is not
describing how full the box looks. It is choosing the box.
Three methods, not one
A space factor is a property of an enclosure, so it does not transfer to tray, ladder or
basket. Open containment is normally sized on the width the cables occupy laid out in a single
layer — the sum of the outer diameters if they are touching, or the diameters plus the clear
gaps if they are spaced at half, one or two diameters.
Trunking and duct are sized on area against a space factor. Tray, ladder and basket are normally sized on the width a single layer occupies — a different calculation, not a different number.
Conduit: the one that is not a percentage
Conduit is the type most people size by eye, and it is the one where eye and rule diverge
most. GN1 Appendix A gives each cable a dimensionless cable factor and each
conduit size a conduit factor; the cables fit if the factors sum to no more than
the conduit's. What makes it different from every other method is that the conduit factor is not
a property of the conduit alone — it drops as the run gets longer and as bends are added, because
the criterion is not "do they fit in the bore" but "can you pull them in without damaging them".
There are two regimes and they use different numbers for the same cable. A run up to 3 m
with no bends reads Tables A1 and A2; anything longer, or with any bend at all, reads Tables A3
and A4 — where the same 2.5 mm² conductor is worth a smaller factor and the conduit is
worth much less. That is why twelve cables that pass in a 25 mm conduit over a short
straight drop need 32 mm once the run is 6 m with two bends. Nothing about the cables
changed. If a run pushes you past the tables, the answer is a draw-in box, not a bigger number:
splitting the run restarts the length and bend count.
Two details are worth getting right. First, the spacing allowance belongs
between cables, not after the last one: five 10 mm cables at 2D spacing need
5 × 10 + 4 × 20 = 130 mm of tray, not
150. Second, if you bunch the cables on the tray rather than laying them out, you are back to an
area calculation — and you have also given up the single-layer grouping factors, which is
usually the more expensive half of that decision.
The fill is an input to the cable size
This is the step that gets missed. Choosing the containment decides how many circuits are
bunched together, and that sets the grouping factor Cg from BS 7671
Table 4C1. Cg multiplies down the current-carrying capacity of every cable in
the group, so the containment decision reaches straight back into the cable schedule.
Circuits per group across the top.
Conduit and trunking are not a separate table — they are item 1, "enclosed".
Note 2 to the table: where the horizontal clearance between adjacent cables
exceeds twice their overall diameter, no factor need be applied at all.
The numbers are blunt. Nine circuits bunched in trunking keeps half of each
cable's tabulated rating; the same nine in a single layer on a ladder keep 0.78. And Note 2
is the get-out worth knowing: space the cables by more than twice their diameter and the factor
disappears entirely. A wider tray with the cables spaced is frequently cheaper than the larger
conductors that bunching would force you into — which is a containment decision made for a cable
reason, and the reason the two calculations belong together.
What else is in the trunking
Fill is not the only thing that decides whether cables may share a containment.
Regulation 528.1 keeps Band I circuits (ELV, data, signalling) out of
the same wiring system as Band II circuits (LV power) unless every Band I
cable is insulated for the highest voltage present, or the two are separated by a partition or run
in separate compartments. Cables of a fire safety service are dealt with
separately again by Section 560, which requires them to be kept apart from other circuits —
and their supports have to keep holding them up during a fire, which is
BS 8519's territory.
A multi-compartment trunking is the usual answer, and it changes the sum: each compartment is its
own fill calculation, not a share of one big section.
Doing it on a real job
Reserve the spare before you choose the size, not after. BS 7671 names
no figure; 20–30 % is common on risers and main routes. Setting it aside first means the
size you specify has the spare in it rather than being at its limit on day one.
Use the real cable diameters. Overall diameter varies between
manufacturers and between an LSOH and a SWA version of the same conductor size — sometimes by
enough to change the containment size. Take them from the datasheets for the cables actually
specified.
Count the layers. The width method assumes one. If the cables are
two deep the single-layer grouping factors no longer apply, and you should be using the bunched
figure or a wider containment.
Carry the weight forward. The cables in the containment are a load on
the supports, and the support spacing follows from it — see
the MEP bracket calculator for the
BS 8519 side of that.
Record the assumptions. The space factor used, the spare allowed and
the cable data source belong on the calculation, because they are the things a checker will
want to see and the things that change between revisions.
Try the numbers on your own route. The
containment fill calculator sizes
trunking, duct, tray, ladder and basket from a cable schedule, applies the space factor and your
spare allowance, reports the Cg your fill implies, and prints a calculation record.
Every value in it is indicative and carries a VERIFY note — confirm them against the products
actually specified before the calculation is issued.
Frequently Asked Questions
Why is trunking limited to 45% fill?
Because cables cannot use the whole section. Round cables cannot tile a rectangle — even a perfect hexagonal stack of identical circles leaves about 9 per cent air, and a real mixed bundle settles well short of that. The cables also have to be drawn in without forcing them past each other, and the remaining air is part of how the heat escapes. The 45 per cent for trunking and 35 per cent for duct come from IET Guidance Note 1 Appendix A, and they are the design rule, not slack in the calculation. Conduit is the exception: GN1 sizes it by summing a cable factor per cable against a conduit factor for the size, run length and number of bends, which is a drawing-in test rather than a fill percentage.
My trunking passes but looks half empty — is that right?
Yes, and it is the most common misreading of a fill calculation. Twelve 10 mm cables in a 50 by 50 mm trunking occupy about 41 per cent of the internal section, which sounds like plenty of room. But 41 per cent of the section is 91 per cent of what the 45 per cent space factor permits. The picture and the percentage are answering two different questions, and only one of them is the rule.
Does the space factor apply to cable tray and basket?
Not normally. A space factor is a fill limit for an enclosed system. Open containment is sized on the width the cables occupy in a single layer: the sum of the outer diameters for cables laid touching, or the diameters plus the clear spacing for cables laid half, one or two diameters apart. The area method returns only if you bunch the cables rather than laying them out — at which point the single-layer grouping factors stop applying too.
How much spare capacity should I leave?
BS 7671 gives no figure — it is a project decision, and 20 to 30 per cent is common on risers and main routes where cables get added later. Reserve it before you choose the size rather than after, so the containment you specify has the spare set aside instead of being at its limit on the day it is installed. Many employer's requirements name a percentage, so check the specification first.
Does filling the containment change the cable size?
Yes, and this is the step that gets skipped. The number of circuits sharing the containment sets the grouping factor Cg from BS 7671 Table 4C1, and Cg multiplies down every cable's current-carrying capacity. Nine circuits bunched in trunking keeps only half. Cable size and containment size are not two separate calculations — the fill you choose is an input to the cable sizing, and a bigger containment with the cables spaced can be cheaper than the larger cables that bunching would demand.
Can power and data cables share a trunking?
Only under conditions. Regulation 528.1 requires that Band I circuits (ELV, data, signalling) and Band II circuits (LV power) are not placed in the same wiring system unless every Band I cable is insulated for the highest voltage present, or the two are separated by a partition or run in separate compartments. Cables of a fire safety service are governed separately by Section 560, which requires them to be kept apart from other circuits — and their supports have to survive a fire, which is where BS 8519 comes in.
Sources and verification. IET Guidance Note 1 Appendix A (space factors and
the trunking capacity tables); BS 7671:2018+A4:2026 Regulation 528.1 (Band I and Band II
segregation), Section 560 and Regulation 560.7.1 (fire safety services), Appendix 4 Table 4C1
items 1–4 and its Note 2, and Table 4C4 (spaced tray and ladder). Cable dimensions are
indicative catalogue values. Confirm every figure against the products actually specified
before a calculation is issued.
Need the containment package produced and checked?
Cable schedules, containment sizing, fill calculations and the support design — produced as an
issue-ready pack. Based in London, working for contractors across the UK.