Design Input Checklist
What to gather before commissioning outsourced electrical design — complete inputs mean faster delivery and a lower quote.
Incomplete input data is the number one cause of delay and cost creep in outsourced design work. Use this checklist to gather what your designer needs — whichever consultancy you use.
📐 Which RIBA stage are you at?
The RIBA Plan of Work 2020 runs from Stage 0 to Stage 7. Expand the stage your project is at to see the electrical services deliverables expected, and tick Yes / No / N/A against each as a design-deliverables audit. Structured on the BSRIA BG 6 Design Framework for Building Services and CIBSE guidance; indicative — verify against your agreed Schedule of Services. Most detailed electrical design lands at Stage 3–4.
0 Stage 0 · Strategic Definition — are you still deciding whether the project goes ahead?
Stage purpose. The business case and strategic brief are established and the client decides whether — and on what basis (new build, refurbishment, extension) — to proceed.
Design deliverables audit — tick Yes / No / N/A for each item:
| Electrical deliverable | Yes | No | N/A |
|---|---|---|---|
| Supply & capacity | |||
| High-level electrical load appraisal for the options being considered | |||
| Review of available / existing supply capacity and likely DNO connection or reinforcement | |||
| Space & budget | |||
| Space allowances for main electrical plant (substation, main switchroom, standby generator) | |||
| Order-of-cost / feasibility input to the business case | |||
| Strategy & risk | |||
| Site-wide electrical constraints and opportunities flagged (resilience, EV charging, renewables) | |||
| Sustainability / energy ambitions noted to steer the electrical strategy | |||
1 Stage 1 · Preparation & Briefing — have you fixed the brief, site information and budget?
Stage purpose. The project brief, feasibility studies, site information, budget and programme are confirmed and the project team is assembled.
Design deliverables audit — tick Yes / No / N/A for each item:
| Electrical deliverable | Yes | No | N/A |
|---|---|---|---|
| Brief & responsibilities | |||
| Electrical section of the project brief / employer's requirements | |||
| Design-responsibility matrix and scope for the electrical package | |||
| Load & supply | |||
| Preliminary load estimate and standby / resilience requirements | |||
| Early DNO enquiry / budget point-of-connection request | |||
| Surveys & standards | |||
| Review of site surveys, existing installations and constraints | |||
| Applicable standards confirmed (BS 7671, BS EN 62305, BS 5266, BS 5839, CIBSE guides) | |||
2 Stage 2 · Concept Design — are you developing the architectural concept and services strategy?
Stage purpose. The architectural concept, outline specification, project strategies and cost plan are prepared and signed off.
Design deliverables audit — tick Yes / No / N/A for each item:
| Electrical deliverable | Yes | No | N/A |
|---|---|---|---|
| Reports & strategy | |||
| Outline electrical strategy / design narrative (Stage 2 report) | |||
| Estimated maximum demand and main supply methodology (LV / HV, metering) | |||
| Drawings | |||
| Concept single-line diagram (intake to main distribution) | |||
| Outline lighting, small power and containment concept layouts | |||
| System concepts | |||
| Outline lighting and lighting-control concept with target lux levels | |||
| Outline fire detection & alarm and emergency-lighting concept | |||
| Outline earthing and lightning-protection (BS EN 62305) approach | |||
| Space & cost | |||
| Main plant, switchroom and riser space requirements | |||
| Elemental / budget cost input to the cost plan | |||
3 Stage 3 · Spatial Coordination — is the design being coordinated across disciplines?
Stage purpose. The design is spatially coordinated across disciplines, strategies and the cost plan are updated, and the design is frozen at the end of the stage.
Design deliverables audit — tick Yes / No / N/A for each item:
| Electrical deliverable | Yes | No | N/A |
|---|---|---|---|
| Calculations & schedules | |||
| Elemental load assessments and diversified load schedules | |||
| Fault-level calculations; preliminary cable sizing and volt-drop checks | |||
| Drawings & schematics | |||
| Developed single-line diagrams and distribution schematics | |||
| Lighting, small power and containment layouts coordinated with structure and other services | |||
| Plant room, switchroom and riser layouts fixed spatially | |||
| Systems & supply | |||
| Fire alarm, emergency lighting and specialist systems (data, security) developed | |||
| Earthing and lightning-protection design updated | |||
| Formal DNO application / supply agreement progressed | |||
| Reports | |||
| Stage 3 report; design coordinated and frozen | |||
4 Stage 4 · Technical Design — do you need construction-ready information?
Stage purpose. All design information is completed and specifications plus specialist / subcontractor design are produced ready for construction.
Design deliverables audit — tick Yes / No / N/A for each item:
| Electrical deliverable | Yes | No | N/A |
|---|---|---|---|
| Calculations | |||
| Full cable sizing and protective-device selectivity / discrimination to BS 7671 | |||
| Fault-level, volt-drop and earth-fault-loop impedance verification | |||
| Lighting and emergency-lighting calculations (lux, uniformity, escape routes) | |||
| Earthing and lightning-protection risk assessment & design (BS EN 62305) | |||
| Drawings & schematics | |||
| Final single-line diagrams and distribution schematics | |||
| Coordinated lighting, small power, containment and fire-alarm layouts | |||
| Builder's-work and containment coordination drawings | |||
| Schedules & specifications | |||
| Distribution board, luminaire and equipment schedules | |||
| Electrical specifications (general & particular) | |||
| Tender / construction-issue documentation | |||
5 Stage 5 · Manufacturing & Construction — are you on site or building?
Stage purpose. Manufacturing and construction proceed in line with the construction programme and design queries are resolved.
Design deliverables audit — tick Yes / No / N/A for each item:
| Electrical deliverable | Yes | No | N/A |
|---|---|---|---|
| Design support | |||
| Respond to technical queries / RFIs and design-change requests | |||
| Review contractor / subcontractor design-portion and installation drawings | |||
| Review manufacturer / specialist submittals and samples against the specification | |||
| Change control | |||
| Reissue calculations, schedules and drawings for site changes / value engineering | |||
| Keep the single-line diagram and load schedule current as the design develops | |||
| Site & quality | |||
| Site inspections and design witnessing as required | |||
| Witness / review testing and commissioning as installation completes | |||
6 Stage 6 · Handover — is the building being handed over?
Stage purpose. The building is handed over, aftercare is initiated and the building contract is concluded.
Design deliverables audit — tick Yes / No / N/A for each item:
| Electrical deliverable | Yes | No | N/A |
|---|---|---|---|
| Records | |||
| As-installed drawings, schematics and calculations | |||
| Input to O&M manuals and the health & safety file | |||
| Verification & close-out | |||
| Review of inspection, testing and certification results (BS 7671 EIC, commissioning records) | |||
| Support snagging and defect close-out; witness demonstrations if required | |||
7 Stage 7 · Use — is the building occupied and in use?
Stage purpose. The building is operated, maintained and occupied, with post-occupancy evaluation.
Design deliverables audit — tick Yes / No / N/A for each item:
| Electrical deliverable | Yes | No | N/A |
|---|---|---|---|
| Aftercare | |||
| Post-occupancy support and aftercare | |||
| Fine-tuning of lighting and controls in response to actual occupancy | |||
| Ongoing | |||
| Re-assessment if loads, occupancy or the supply change | |||
| Input to periodic inspection & testing (EICR) and maintenance regimes | |||
References: RIBA Plan of Work 2020 — overview & free PDF · ribaplanofwork.com · BSRIA BG 6 — Design Framework for Building Services. Stage names and purposes follow the RIBA Plan of Work 2020 (which is discipline-agnostic — RIBA does not itself publish an electrical deliverables list). The electrical deliverables audited above are structured on the BSRIA BG 6 framework and CIBSE guidance; they are indicative typical outputs, not a verbatim reproduction, and the exact split varies by project and appointment.
⏚ For an Earthing Study
- Site layout drawing (DWG or PDF) showing substation / electrode locations
- Soil resistivity survey results — Wenner or Schlumberger, with probe spacings and date
- Earth fault level and fault clearance time (from the DNO or protection study)
- Supply earthing arrangement and DNO connection details / offer letter
- Existing earthing system drawings, if working on a live or brownfield site
- Nearby third-party infrastructure within ~100 m — rail, pipelines, telecoms, fences
- Applicable specifications — client spec, National Grid, LU, HS2, ENA documents
- Programme deadline, especially any DNO submission date
⚡ For a Cable Calculation Pack (ProDesign)
- Single-line diagram or schematic (even a marked-up sketch helps)
- Load schedule with ratings and any diversity assumptions
- Cable routes and lengths, or a layout drawing to measure from
- Supply details — transformer rating, fault level, earthing system (TN-S, TN-C-S…)
- Installation methods — tray, ladder, clipped, buried — and grouping
- Preferred cable types and protective device manufacturer/ranges
- Client specification and applicable project standards
- Existing ProDesign / Amtech project files, if the design is being updated
💡 For a Lighting Design (DIALux)
- Floor plans (DWG preferred, PDF workable) with room names
- Ceiling heights, and surface finishes/reflectances if known
- Target lux levels or the standard to design to (BS EN 12464, client spec)
- Preferred luminaire manufacturer or wholesaler ranges
- Emergency lighting requirements and escape routes, if in scope
Missing some of it? Send what you have — we'll tell you exactly what's still needed and whether we can proceed with stated assumptions. See our pricing guide for how input completeness affects cost.