Voltage Drop to BS 7671: The 3% and 5% Limits (Reg 525)
Cable Sizing · Updated 31 July 2026 · For contractors and project engineers
A cable big enough to carry the current can still be too small. By the time the supply reaches
the far end of a long run the voltage has sagged, and the equipment there sees less than it was
designed for. BS 7671 puts a limit on that sag — and the limit is not a single number. It
depends on what the circuit serves, where the supply comes from, and how long the wiring system
is. Here is how the rule actually reads, how to calculate the drop, and the two places designs
most often go wrong.
The short version: keep the drop within 3% for lighting and
5% for everything else on a public supply, measured
from the origin of the installation to the terminals of the equipment — so it is
cumulative across sub-mains. Work it out with
Vd = mV/A/m × Ib × L / 1000.
Two things catch people out: a private supply gets 6% / 8% but each final circuit still owes
3% / 5%, and past 100 m the limits themselves relax slightly.
Try it: the voltage drop explorer
Set a circuit up and watch the voltage profile from the origin to the equipment. Drag the
length past 100 m and the limit line itself moves. Switch the supply to a sub-main feed and
the two legs start sharing one budget — which is the failure mode this page exists to explain.
This interactive explorer needs JavaScript. Everything it demonstrates is also covered by the
figures, tables and worked examples below.
The limits — Appendix 4, Table 4Ab
Regulation 525.1 requires the voltage at the terminals of any equipment to be no less than the
lower limit of that equipment's own standard. Regulation 525.201 says that requirement is met
if the drop does not exceed the values in Appendix 4, and those values live in
Table 4Ab. There are two rows, and which one applies depends on where the
supply comes from, not on the size of the installation.
The limit depends on where the supply comes from. A private LV supply buys headroom for the distribution, not for the final circuit — the footnote to row (b) still holds every final circuit to the 3% / 5% values.
BS 7671 Appendix 4, Table 4Ab — permitted voltage drop, as a percentage of the nominal voltage
Supply
Lighting
Other uses
At 230 V
At 400 V
(a) Direct from a public LV distribution system
3%
5%
6.9 V / 11.5 V
12 V / 20 V
(b) From a private LV supply *
6%
8%
13.8 V / 18.4 V
24 V / 32 V
* The footnote to row (b) is the part that gets missed: the drop within
each final circuit must still not exceed the row (a) values. A private supply — your own
transformer, a generator, a site supply — buys headroom for the distribution, because
you control the source voltage. It does not relax the final circuit.
The allowance beyond 100 metres
Beneath the table sits a sentence almost no online calculator implements. Where the wiring
systems of the installation are longer than 100 m, the permitted drop may be increased by
0.005% per metre beyond 100 m, and that increase may not exceed
0.5%. So the 5% limit becomes 5.25% at 150 m and 5.5% at 200 m — and
then stops, because 100 m beyond the threshold at 0.005%/m is exactly the 0.5% cap. Past
200 m the limit never moves again.
What the allowance is worth on a 5% limit
Wiring system length
Allowance
Permitted drop
100 m or less
—
5.00%
120 m
+0.10%
5.10%
150 m
+0.25%
5.25%
200 m
+0.50%
5.50%
300 m and beyond
+0.50% (capped)
5.50%
It is a small allowance, but on a long run it is often the difference between one cable size and
the next — and it is defensible, because it is in the standard. Claiming it means stating the
wiring-system length you based it on.
Where the drop is measured from, and to
Regulation 525.202 names both ends: from the origin of the installation to the terminals
of the equipment. Not from the distribution board. Not to the accessory. That single
sentence is what makes voltage drop cumulative, and it is where most failures come from —
because each cable was checked on its own and nobody added them up.
Regulation 525.202 measures the drop from the origin of the installation to the terminals of the equipment — so a sub-main and the final circuit it feeds share one budget. Size them separately and they can each pass while the installation fails.
In the figure above the sub-main spends 2.92% and the final circuit 2.87%. Each is comfortably
inside 5%. Together they are 5.79%, and the installation does not comply. The
socket at the end of that circuit does not care which cable spent the budget.
Two practical consequences follow. First, a sub-main is worth uprating even when it passes,
because every circuit downstream inherits whatever it spends — one bigger sub-main is usually
cheaper than five bigger final circuits. Second, a change to a sub-main silently changes every
circuit it feeds, which is exactly the bookkeeping that hand calculations and spreadsheets lose
track of when a design moves.
The current used is the design current Ib — the demand after
diversity, not the rating of the protective device. Sizing voltage drop on In when
the real load is half of it is a common and expensive way to over-specify a cable.
The formula
Every cable size has a tabulated voltage-drop figure in millivolts per ampere per metre
(mV/A/m) in BS 7671 Appendix 4. The drop is:
Vd = (mV/A/m × Ib × L) / 1000
with Ib the design current in amps and L the route length in metres — the length of
the run, not the length of conductor in it; the tabulated values already account for the return
path. Divide by the nominal voltage and multiply by 100 for the percentage. For a three-phase
circuit take the value from the three- or four-core column and express the result against
400 V, not 230 V: a common error is to compute a three-phase drop and
then divide it by the phase voltage, which overstates the percentage by about 73%.
Worked example. A 32 A single-phase radial on 6 mm² PVC
multicore copper, 25 m long. Appendix 4 gives 7.3 mV/A/m.
Vd = 7.3 × 32 × 25 / 1000 = 5.84 V
As a percentage of 230 V: 5.84 / 230 × 100 = 2.54% — inside the 5% limit
for other uses, and inside 3% if it were a lighting circuit. The equipment sees 224.2 V.
Drop to 4 mm² (11 mV/A/m) and it becomes 8.8 V, or 3.83% — still fine for
power, but it would now fail as a lighting circuit. Drop to 2.5 mm²
(18 mV/A/m) and it is 14.4 V, 6.26%, which fails outright.
Above 16 mm², power factor enters
For conductors larger than 16 mm² the tables stop giving a single value and split it
into a resistive part (mV/A/m)r and a reactive part (mV/A/m)x, because the
conductor's inductance is no longer negligible next to its resistance. Appendix 4 §6.2(b)
combines them with the load's power factor:
(mV/A/m) = (mV/A/m)r × cos θ + (mV/A/m)x × sin θ
where cos θ is the power factor. The single (z) figure tabulated for large cables assumes
unity power factor and is the pessimistic case for the resistive component; at a poor power
factor the reactive term matters and the answer changes. Below 16 mm² the single value
is used directly and this refinement does not arise.
mV/A/m reference values
A working subset of the Appendix 4 tables for the cables that come up most often. The first
figure in each cell is the single-phase (two-core) value, the second the three-phase
(three- or four-core) value. Aluminium is not tabulated below 16 mm².
Voltage drop in mV/A/m — single-phase / three-phase, indicative subset of BS 7671 Appendix 4
Cable
1 mm²
1.5 mm²
2.5 mm²
4 mm²
6 mm²
10 mm²
16 mm²
25 mm²
35 mm²
50 mm²
70 mm²
95 mm²
PVC 70 °C copper
44 / 38
29 / 25
18 / 15
11 / 9.5
7.3 / 6.4
4.4 / 3.8
2.8 / 2.4
1.75 / 1.5
1.25 / 1.1
0.93 / 0.8
0.63 / 0.55
0.46 / 0.41
XLPE 90 °C copper
46 / 40
31 / 27
19 / 16
12 / 10
7.9 / 6.8
4.7 / 4
2.9 / 2.5
1.85 / 1.6
1.35 / 1.15
1 / 0.86
0.68 / 0.59
0.5 / 0.44
PVC 70 °C aluminium
—
—
—
—
—
—
4.5 / 3.9
2.9 / 2.5
2.1 / 1.8
1.55 / 1.35
1.05 / 0.92
0.77 / 0.68
Indicative values for the reference methods these tools cover — verify every figure against your
own copy of BS 7671 Appendix 4 for the actual cable, installation method and reference table.
What conductor size actually does
The same circuit at three sizes. Voltage drop is the one check that ignores how good your protective device is — the only levers are a bigger conductor, a shorter route, or less current.
Voltage drop is the odd one out among the checks in a cable calculation. Current-carrying
capacity can be rescued by a better installation method; earth-fault loop impedance can be
rescued by a more sensitive device. Voltage drop has only three levers — a bigger conductor, a
shorter route, or less current — and no protective device, however good, changes the answer.
The relationship is close to inverse: mV/A/m falls by roughly 60% each time you go up two
standard sizes, so going from 2.5 to 4 mm² cuts the drop by about 39%, and 2.5 to
6 mm² by about 59%. That is why the fix is almost always "one or two sizes up" rather
than a redesign — but on a long run, one size up on a sub-main beats one size up on every
circuit behind it.
What the drop actually costs you
The limits are not arbitrary caution. Equipment behaves measurably worse on low voltage, and the
two headline cases behave very differently — which is precisely why lighting gets the tighter
number:
Induction motors — torque falls roughly with the square of the voltage, so a 5% drop costs about 10% of available torque. The motor compensates by drawing more current, which heats it and eats into its own thermal margin. Starting is worse still, because starting torque is where the margin is thinnest.
Filament and halogen lighting — light output falls far faster than voltage, roughly as V3.4, so 5% less voltage is about 16% less light. That is the reason for the 3% row.
LED drivers and electronic loads — usually regulate through it, but they draw more current as the voltage falls, which adds to the drop rather than relieving it.
Heating — output falls as the square of the voltage, so a 5% drop costs about 10% of the heat, and the appliance simply runs longer.
Contactors and control gear — dropout thresholds are typically set around 70–80% of nominal, so voltage drop rarely trips them directly, but it eats the margin that a real supply dip would need.
Motor starting is a separate check
Table 4Ab is a steady-state limit. Regulation 525.203 accepts a larger drop for motor starting
and other high-inrush conditions, provided the voltage stays within the limits of the relevant
equipment standard. A direct-on-line motor drawing six or seven times full-load current for a
few seconds will breach the steady-state figure comfortably, and that is expected — but you have
to check it against what the motor and its contactor will actually tolerate, not simply ignore
it. The two checks answer different questions and you need both.
The same logic applies in reverse to harmonics: the drop should include any effect due to
harmonic currents, which on a load with significant third harmonic means the neutral is carrying
current the fundamental calculation never accounted for.
If a circuit fails
Increase the conductor size — the most direct fix; halving the mV/A/m halves the drop.
Uprate the sub-main instead — if several circuits are marginal, the drop they share is the cheapest place to buy headroom.
Shorten the route, or move the distribution board nearer the load centre. A board in the right place is worth more than a cable size.
Split the load across more circuits so each carries less current.
Check the design current — is Ib the real demand after diversity, or did the device rating get used by mistake?
Claim the >100 m allowance if the wiring system genuinely exceeds 100 m, and record the length you based it on.
Check whether the supply is private — an installation on its own transformer gets row (b), subject to the final-circuit footnote.
Where this fits in a cable calculation
Voltage drop is one of the five checks in a compliant
cable calculation, alongside
current-carrying capacity (with its
derating factors),
earth-fault loop impedance,
the adiabatic check on the protective conductor, and breaking capacity against the
prospective fault level.
It is the check most likely to be the binding constraint on a long run, and the one least
forgiving of a design change, because it is cumulative and network-wide.
Our free BS 7671 cable sizing calculator
runs all five for a distribution board and prints a calculation report, and the
kW to amps calculator will get you from a load in
kilowatts to the design current this page starts from.
Glossary
Vd — voltage drop, the difference between the voltage at the origin and at the equipment terminals.
mV/A/m — the tabulated drop per ampere per metre of run, from BS 7671 Appendix 4.
Ib — design current: the demand the circuit is actually intended to carry, after diversity.
In — the rated current of the protective device, which is not what voltage drop is calculated on.
U0 — nominal line-to-neutral voltage, 230 V in the UK.
U — nominal line-to-line voltage, 400 V, the reference for a three-phase drop.
Origin of the installation — where the supply enters and the installation begins; one end of every voltage-drop measurement.
Sub-main — a distribution circuit feeding another board rather than a final load.
cos θ — power factor, needed once the conductor is larger than 16 mm² and reactance matters.
Frequently Asked Questions
What is the maximum voltage drop allowed by BS 7671?
For an installation supplied directly from the public low-voltage network, BS 7671 Appendix 4 Table 4Ab gives 3% for lighting and 5% for other uses, measured from the origin of the installation to the terminals of the equipment. At 230 V single-phase that is 6.9 V and 11.5 V; at 400 V three-phase, 12 V and 20 V.
How do you calculate voltage drop?
Voltage drop = (mV/A/m × Ib × L) / 1000, where mV/A/m is the cable's tabulated value from BS 7671 Appendix 4, Ib is the design current in amps, and L is the route length in metres. Divide the result by the nominal voltage and multiply by 100 to get the percentage. For a three-phase circuit use the three- or four-core column and express the answer against 400 V, not 230 V.
Is voltage drop measured per circuit or from the origin?
From the origin of the installation to the terminals of the equipment, so it is cumulative. Regulation 525.202 is explicit about the two end points. The drop across a sub-main and the final circuit it feeds must be added together and the total kept within the limit — which is why a final circuit that passes comfortably on its own can still put the installation over.
Does the 3% or 5% limit ever increase?
Yes. Where the wiring system of the installation is longer than 100 m, Table 4Ab allows the limits to be increased by 0.005% per metre beyond 100 m, up to a maximum increase of 0.5%. So a 5% limit becomes 5.25% at 150 m and 5.5% at 200 m, after which the allowance stops growing because it has hit its cap.
Do the limits change for a private supply?
Yes. Where the installation is fed from a private LV supply — its own transformer or a generator rather than the public network — Table 4Ab allows 6% for lighting and 8% for other uses. But the footnote to that row still requires the drop within each final circuit not to exceed the 3% and 5% values, so the extra headroom is for the distribution, not for the final circuit.
What happens if the voltage drop is too high?
Equipment receives less voltage than it was designed for. Induction motor torque falls roughly as the square of the voltage, so a 5% drop costs about 10% of torque, and motors draw more current to compensate, which heats them. Filament lamp output falls faster still. Electronic equipment usually copes but its input current rises. Long-term the risk is nuisance tripping, overheating and shortened equipment life rather than an immediate failure.
What do I do if a circuit fails the voltage drop check?
Increase the conductor size, shorten the cable route, move the distribution board nearer the load centre, or split the load across more circuits. On a network it is often cheaper to uprate one sub-main than several final circuits, because every circuit downstream inherits the sub-main's drop. Check the assumptions too — is the full design current really continuous, and is the route as long as assumed?
Why do voltage drop tables split into r and x above 16 mm²?
Because above 16 mm² the conductor's inductive reactance becomes significant next to its resistance, so the drop depends on the load's power factor. Appendix 4 section 6.2(b) gives the combined value as (mV/A/m)r × cos θ + (mV/A/m)x × sin θ, where cos θ is the power factor. Below 16 mm² the reactance is small enough that the single tabulated z value is used directly.
Does voltage drop apply during motor starting?
The limits are for normal steady-state service. Regulation 525.203 accepts that a greater drop is allowed for motor starting and other high-inrush currents, provided the voltage stays within the limits specified in the relevant equipment standard. In practice you check the running condition against Table 4Ab and check starting separately against what the motor and its contactor will actually tolerate.
Sources and verification. BS 7671:2018+A4:2026 Regulations 525.1, 525.201,
525.202 and 525.203; Appendix 4 §6.2 and §6.4 and Table 4Ab for the limits; Appendix 4 Tables
4D2B, 4E2B, 4H2B and 4J2B for the mV/A/m values. The figures on this page are an indicative
subset for explanation — verify every value against your own copy of BS 7671 for the actual
cable, installation method and reference table, and remember the drop should include any effect
due to harmonic currents.
Cable Sizing That Adds It Up For You
Our free BS 7671 calculator runs the five checks and prints a calculation report. Or hand the whole network over to us and get voltage drop checked cumulatively across every circuit.