A cable that's big enough to carry the current can still be too small — because by the time the supply reaches the far end of a long run, the voltage has sagged below what the equipment needs. BS 7671 puts a limit on that sag. Here's how the 3% and 5% rules work, how to calculate voltage drop, and what to do when a circuit fails it.

The short version: keep the drop from the origin to the load within 3% for lighting and 5% for everything else (public supply). Work it out with VD = mV/A/m × Ib × L / 1000, and remember it's cumulative — submain plus final circuit.

The Limits (Regulation 525)

For an installation supplied directly from the public LV network, the permitted voltage drop from the origin to any point of use is:

CircuitLimit230 V400 V
Lighting3%6.9 V12 V
Other uses (power)5%11.5 V20 V

Fed from a private source (own transformer or generator) instead of the public network, the limits rise to 6% and 8%.

The Formula

Every cable size has a tabulated voltage-drop figure in millivolts per ampere per metre (mV/A/m) in BS 7671 Appendix 4. The drop is:

Vd = (mV/A/m × Ib × L) / 1000

with Ib the design current and L the length in metres. For sizes of 25 mm² and above the tables split the value into resistive (r) and reactive (x) parts because inductance starts to matter, and you combine them with the load's power factor; below that, the single (z) figure is fine.

Worked example: a 32 A circuit on 4 mm² twin-and-earth (11 mV/A/m) over 25 m drops 11 × 32 × 25 / 1000 = 8.8 V, which is 3.8% of 230 V. Fine as a power circuit (under 5%), but it would fail the 3% lighting limit — you'd move to 6 mm² or shorten the run.

It's Cumulative — Origin to Load

The limit applies to the whole path, not each circuit in isolation. A final circuit fed through a long submain shares the submain's drop, so a final circuit that passes on its own can fail once the submain is added. On a real network this bookkeeping is where hand calculations go wrong — the drop at a socket depends on every cable upstream of it, and a change to the submain silently changes every circuit it feeds.

If a Circuit Fails

  • Increase the conductor size — the most direct fix; halving the mV/A/m roughly halves the drop.
  • Shorten the route or move the distribution board closer to the load centre.
  • Split the load across more circuits so each carries less current.
  • Check the assumption — is the full design current really continuous, and is the route length as long as assumed?

Where This Fits

Voltage drop is one of the five checks in a compliant cable calculation, alongside current-carrying capacity (with derating factors), earth-fault loop impedance and the adiabatic check. Because it's cumulative and network-wide, it's exactly the sort of thing calculation software gets right and spreadsheets get wrong when a design changes.

Frequently Asked Questions

What is the maximum voltage drop allowed by BS 7671?

For an installation supplied from the public low-voltage network, BS 7671 Regulation 525 limits voltage drop to 3% for lighting and 5% for other uses, measured from the origin of the installation to the load. At 230 V single-phase that is 6.9 V and 11.5 V; at 400 V three-phase, 12 V and 20 V.

How do you calculate voltage drop?

Voltage drop = (mV/A/m × Ib × L) / 1000, where mV/A/m is the cable's tabulated value from BS 7671 Appendix 4, Ib is the design current in amps, and L is the length in metres. Divide the result by the nominal voltage to get the percentage.

Is voltage drop measured per circuit or from the origin?

From the origin of the installation to the point of use — so it is cumulative. The drop across a submain and the final circuit it feeds must be added together and the total kept within the limit. That is why a final circuit that passes on its own can still fail once the submain drop is included.

What do I do if the voltage drop is too high?

Increase the conductor size, shorten the cable route, move the distribution board nearer the load, or split the load across more circuits. On a network it is often cheaper to uprate one submain than several final circuits.

Do the limits change for a private supply?

Yes. Where the installation is fed from a private source such as its own transformer or a generator rather than the public network, BS 7671 allows higher limits — 6% for lighting and 8% for other uses — because the supply voltage is under the installation owner's control.

Cable Sizing That Includes Voltage Drop

BS 7671 calculation packs that check voltage drop cumulatively across the whole network.

ProDesign Cable Calculations