Maximum Demand & Diversity: What BS 7671 Actually Says
Cable Sizing · Updated 31 July 2026 · For contractors and project engineers
Add up the rating of every circuit in a building and size the supply to match, and you will
specify an incomer two or three times bigger than you need — because not everything runs
flat out at the same moment. Diversity is how you size for the realistic peak instead. What
almost nobody mentions is that BS 7671 does not tell you how. It requires
you to determine maximum demand, permits you to allow for diversity, and then stops.
The short version: Regulation 311.1 is forty-four words and contains no
table, no percentages and no cross-reference to any. The allowances everyone quotes come
from the IET On-Site Guide, which is guidance — and which says of its own table that
it has "not been updated for some time". So diversity is a judgement you own and must be able
to defend, not a lookup you can cite. And whatever you assume, it sizes the
supply: Regulation 536.4.202 requires the board itself to be rated for the
total connected load with no diversity at all.
Try it: the diversity explorer
Build a load schedule, then switch the premises type. The same loads give a different maximum
demand in each column, and the explorer shows which rule fired on each category and what it
took off. That spread is the point: these are conventions for a type of building, not physics.
This interactive explorer needs JavaScript. Everything it demonstrates is also covered by the
figures, worked example and explanation below.
Connected load is not maximum demand
Diversity is the gap between what is connected and what will realistically run at once. It sizes the supply — and only the supply. Regulation 536.4.202 requires the board itself to be rated for the total connected load with no diversity at all.
Connected load is the arithmetic total of everything wired in.
Maximum demand is what you expect to be drawn at the same instant. Diversity
is the gap. In the figure above a small domestic board has 61.7 A connected; the lighting
allowance takes 1.8 A off and the cooker rule takes 23.4 A off, leaving a maximum
demand of 36.5 A that fits comfortably on a 40 A supply.
Note what does not move: the thermostatically controlled immersion heater. It is
already cycling on its own thermostat, so there is nothing further to assume about it, and the
guidance allows it no diversity at all. That pattern — long-duration thermostatic loads keeping
their full value — is the single most important thing to carry into modern work, where heat
pumps and EV chargers behave the same way.
What Regulation 311.1 actually says
Here it is in full. This is the entirety of BS 7671's treatment of maximum demand:
311.1 For economic and reliable design of an installation within thermal
limits and admissible voltage drop, the maximum demand shall be determined. In
determining the maximum demand of an installation or part thereof, diversity
may be taken into account.
Two words carry the weight. Determining maximum demand is "shall" — mandatory.
Applying diversity is "may" — permitted, optional, and entirely unspecified.
There is no Regulation 311.2; Chapter 31 moves straight on to conductor arrangement. If your
demand assessment turns out to be wrong, the failure is against 311.1's "shall", not against
any table.
And the standard is no more forthcoming elsewhere. In 642 pages the word "diversity" appears
fifteen times, and not once with a number attached. There is no diversity table. There is no
"current demand to be assumed" table. There is no cooker allowance. "Maximum demand" is not
even a defined term in Part 2 — though "diversity" is, circularly, as a
"means of determining maximum demand … taking into account usage patterns".
Most tellingly of all: BS 7671 never once tells you where to look. There is no
cross-reference to the On-Site Guide or to any Guidance Note anywhere in the book. Appendix 1
lists British Standards; Appendix 2 lists statutory instruments and HSE publications. The
industry's universal reliance on the On-Site Guide's table is a convention supported by
nothing in the standard's own text.
So where do the numbers come from?
From IET On-Site Guide, Appendix A — "Maximum demand and diversity" — and its
Table A2, "Allowances for diversity". The equivalent material is in Guidance Note 1. Both are
IET publications sold alongside the standard. Neither is the standard.
That would be a pedantic distinction if the guide were confident about its own figures. It is
not. Appendix A opens by saying the values are "intended only for guidance, because it is
impossible to specify the appropriate allowances for diversity for every type of installation
and such allowances call for special knowledge and experience", and then goes considerably
further:
The guide's own health warning. The recommendations in its diversity table
"have not been updated for some time, and do not necessarily align with modern loads
and usages". The values "may be increased or decreased as decided by the installation
designer concerned". And "no guidance is given for blocks of residential dwellings,
large hotels or industrial and large commercial premises" — those "should be assessed
on a case-by-case basis".
Put the two documents together and the position is clear. The standard requires an assessment
and gives no method. The guide gives a method, disclaims it, and declines to cover a large
fraction of the buildings people actually design. Diversity is a judgement you own.
You can defend it with reasoning, load profiles and metered data. What you cannot do is point
at a regulation and say the number came from there.
How the allowances actually work
The most common mistake in software — including, until this week, our own calculator — is to
treat diversity as one percentage per category. It is not. The guide's allowances have three
different shapes, and only one of them is a plain percentage:
A straight percentage of the group. Lighting works this way, and the percentage differs by premises type — roughly two thirds in a house, nine tenths in a shop or office, three quarters in a small hotel. Offices are lit consistently all day; houses are not.
Ranked: the largest in full, then a decreasing share of the rest. Most commercial rows work this way — the biggest appliance or motor counts fully, the second at a reduced fraction, the remainder at a lower one again. It is a bet that the largest single item is the one running.
Banded: everything up to a threshold, then a fraction above it. Domestic heating and other unlisted final circuits take the first 10 A in full and half of anything beyond, so a small load gets no reduction at all and a large one gets a substantial one.
A fixed base plus a share of the excess. The household cooker is the famous one: the first 10 A, plus 30 % of the connected rating above that, plus a further 5 A if there is a socket-outlet in the cooker control unit. A 43.5 A cooker comes down to 20 A.
Nothing at all. Thermostatically controlled water heating and floor warming get no diversity in any column. They are already self-regulating; there is no second assumption to make.
None of those can be expressed as a single multiplier, which is why a calculator that uses one
will disagree with a hand calculation. Our
maximum demand calculator now applies the
staged rules and shows the working for each category, so you can see which rule fired rather
than being handed a number.
Same schedule, three answers
One schedule, three answers — and BS 7671 has no opinion on which is right, because it publishes no allowances at all. The household column bands the cooker down hard; the commercial columns rank it and take almost nothing off.
This is the part worth internalising. The guide gives three columns — individual households
including individual dwellings of a block; small shops, stores, offices and business premises;
and small hotels, boarding houses and guest houses — and the same load schedule can produce
wildly different maximum demands depending on which one you use.
The 61.7 A domestic board above comes out at 36.5 A on the household column and just
over 61 A on either commercial column: the difference between a 40 A incomer and a
63 A one. The reason is the cooker. The household rule bands it down to 20 A; the
commercial rules rank it, and with a single cooker "100 % of the largest appliance" means
no reduction whatsoever.
Choosing the wrong column costs more than choosing the wrong method — and
remember the guide offers no column at all for a block of flats, a large hotel, a factory or a
large commercial building. If that is your job, the table does not cover you and the assessment
is entirely yours.
A worked example
Worked example — a domestic consumer unit. 1.2 kW of lighting,
a 10 kW cooker and a 3 kW immersion heater, all single-phase at 230 V.
Connected: 5.2 + 43.5 + 13.0 = 61.7 A
Lighting: 5.2 × 0.66 = 3.4 A
Cooker: 10 A + 30 % of the 33.5 A above it = 20.0 A
(add 5 A if there is a socket in the control unit)
Immersion heater: thermostatic, so no diversity — 13.0 A
Maximum demand: 36.5 A → a 40 A supply is enough.
But the consumer unit must still be rated for all 61.7 A.
Diversity sizes the supply, never the board
The standard says far more about where diversity may not be used than about how to use it — and Amendment 4 tightened it further. An assumption is never a substitute for a control.
This is where Amendment 4 quietly tightened things, and it is the half of the subject that
almost never gets written about. Regulation 536.4.202 gives three routes to
protecting a low-voltage switchgear and controlgear assembly — which the regulation's own note
confirms includes a distribution board and a consumer unit — against overload. One of them is:
"The total connected load without diversity does not exceed the rated current
of the assembly (InA) and any outgoing unit (Inc)."
And then, unambiguously: "Diversity shall not be used as a means of load curtailment,
load control or overload protection."
So the assessment you use to size the incomer is not the assessment that sizes the board. If
you take that route, the board carries everything bolted to it. The alternatives are that the
upstream protective device is rated at or below the assembly's rating, or that real load
curtailment limits the demand — and curtailment means an engineered control, not an assumption.
Where BS 7671 does and does not let you rely on diversity
Where
Diversity?
Regulation
What it says
Sizing the supply and the incomer
Permitted
Reg 311.1
The one place the standard positively permits it — and it still gives no method.
Sizing an RCCB, switch or transfer switch
Permitted
Reg 536.4.3.2
May be based on applying diversity factors to the downstream circuits "according to Regulation 311.1".
Rating the distribution board or consumer unit
Not permitted
Reg 536.4.202
One compliance route is the total connected load without diversity not exceeding InA and Inc.
As load curtailment, load control or overload protection
Not permitted
Reg 536.4.202
Stated outright: diversity shall not be used as a means of any of the three.
An assembly with a generator running in parallel
Not permitted
Reg 551.7.2.2
Rated on Itcl, the total connected load without diversity, including exported current.
Electric vehicle charge points
Not permitted
Reg 722.311.201
Section 722 offers load curtailment — an engineered control — not an allowance.
Note the circularity in the one permissive case: Regulation 536.4.3.2 is the only normative
sentence in BS 7671 that uses the phrase "diversity factors", and it permits them "according to
Regulation 311.1" — which supplies none. Regulation 551.7.2.2 repeats the "without diversity"
rule for an assembly with a generator in parallel, and requires a warning notice stating the
maximum permitted connected load.
The switchboard's own "diversity factor" is a different thing
Assemblies to BS EN 61439 carry a rated diversity factor, and it trips people
up because it wears the same word. The standard defines it as:
"the per unit value of the rated current, assigned by the assembly manufacturer, to which
outgoing circuits of an assembly can be continuously and simultaneously loaded taking into
account the mutual thermal influences"
Read that carefully. It is a thermal limit on the enclosure — how much of each
circuit's rating can be drawn at the same time before the assembly overheats — and it
is declared by the manufacturer, not chosen by the designer. It says nothing at all about
whether the loads will in practice run together. Expressed as a formula it is simply the
operating current over the circuit's rated current, and the default values by number of
circuits are tabulated in BS EN 61439-2. Read them there; we do not reproduce figures we have
not verified against the source.
The two quantities are orthogonal, and the failure mode is treating the assembly's rated
diversity factor as diversity you have "already claimed", or vice versa. They answer different
questions and both have to be satisfied.
EV charging, heat pumps, and why the old habits now bite
The diversity table was written for a world of intermittent loads. Two modern additions break
its assumptions, and the standard has responded to only one of them.
EV charge points — Reg 722.311.201. Section 722 does not offer a diversity allowance. It permits load curtailment — "load reduction including disconnection, either automatically or manually" — to be taken into account when determining maximum demand. Combined with 536.4.202's prohibition on using diversity as a means of load curtailment, the conclusion is unavoidable: you may install a load-management system and count it, but you may not simply assume the chargers will not coincide.
Heat pumps — nothing at all. BS 7671:2018+A4:2026 does not mention heat pumps anywhere: not a section, not a regulation, not an index entry, in a standard amended in 2026. The On-Site Guide's table predates them. A heat pump is a long-duration thermostatically controlled load, so the closest analogous row is the one allowing no diversity — treat it as near-continuous unless you have real data.
Everything else that runs all day. Server rooms, commercial refrigeration, electric boilers. The common thread is duration: diversity is a bet about coincidence, and loads that run for hours coincide.
This is why so many boards that were "adequate" now need upgrading. Adding a 32 A charge
point to an installation is not adding 32 A of diversified load — it is adding 32 A.
On three phases, balance matters as much as total
A three-phase maximum demand is not one number. The incomer and the tails are sized on the
governing phase — the busiest one — so an installation can be well within its
supply on average and over it on one line. The explorer above reports the per-phase figures and
the imbalance percentage alongside the total.
Two consequences. First, moving one large single-phase load between lines can reduce the
maximum demand without changing the connected load at all — the cheapest capacity you will ever
find. Second, imbalance drives the neutral current, which is its own design question once
harmonics are involved: see the
derating factors article on triplen
harmonics, where above a third-harmonic threshold you size on the neutral rather than the line.
ADMD is a different quantity
After Diversity Maximum Demand is what a distribution network operator uses across a group of
dwellings, quoted as kW or kVA per property. It diversifies across many households
whose peaks fall at different times, so it falls as the number of properties rises — the
opposite direction from the installation diversity above, which is fixed by category.
They are not interchangeable. Sizing one property's tails on an ADMD figure will undersize
them; sizing a network on one property's installation diversity will oversize it substantially.
And note that the On-Site Guide explicitly declines to give guidance for blocks of dwellings —
exactly the case where people reach for ADMD instead.
What it costs to get it wrong
Maximum demand sizes the incomer, the main tails, the distribution transformer or standby
generator, and the DNO connection. Overestimate it and the client pays for capacity and copper
they will never use. Underestimate it and the main protection operates, or the connection is
too small to extend later — and a DNO upgrade is one of the slowest and most expensive changes
to make after the fact.
The design current that comes out of this assessment is the Ib that every downstream
check consumes: the five checks of a
cable calculation, voltage drop, and
the rating factors applied to
current-carrying capacity. Get demand wrong and every one of them is wrong with it. If you are
starting from loads in kilowatts, the
kW to amps calculator will get you to the
currents this assessment starts from — it deliberately does not apply diversity, because that
is the judgement described on this page.
Glossary
Connected load — the arithmetic total of everything wired in, with no allowance for coincidence.
Maximum demand — the current expected at the same instant. Not defined in BS 7671 Part 2, despite Reg 311.1 requiring it.
Diversity — "means of determining maximum demand … taking into account usage patterns" (BS 7671 Part 2).
Ib — design current: the demand this assessment produces, and the input to every downstream check.
f.l. — full load: an allowance expressed as a percentage of an appliance's rated full-load current rather than of the group's demand.
ADMD — After Diversity Maximum Demand: the network operator's figure per dwelling, across many properties.
InA / Inc — the rated current of an assembly, and of an outgoing unit within it (Reg 536.4.202).
Load curtailment — "load reduction including disconnection, either automatically or manually" (BS 7671 Part 2). A control, not an assumption.
Rated diversity factor — BS EN 61439's thermal limit on how much of an assembly's circuits may be loaded simultaneously. Not load diversity.
Frequently Asked Questions
What does BS 7671 say about diversity?
Regulation 311.1, in its entirety: "For economic and reliable design of an installation within thermal limits and admissible voltage drop, the maximum demand shall be determined. In determining the maximum demand of an installation or part thereof, diversity may be taken into account." That is forty-four words, and it is all of it. Determining maximum demand is mandatory; applying diversity is optional; and the standard gives no method, no table and no cross-reference to one.
Is the diversity table in BS 7671?
No. There is no diversity table anywhere in BS 7671:2018+A4:2026, and no "current demand to be assumed" table either. The word "diversity" appears fifteen times in 642 pages and never once with a number attached. The familiar allowances — 66 per cent of the lighting, the cooker's first 10 A plus 30 per cent of the remainder — are in the IET On-Site Guide, Appendix A, which is guidance rather than the standard.
What is the difference between connected load and maximum demand?
Connected load is the arithmetic total of everything wired in. Maximum demand is what you expect to be drawn at the same moment, which is smaller because not everything runs at once. Diversity is the difference between the two. The distinction matters legally as well as commercially: maximum demand sizes the supply, but Regulation 536.4.202 requires the distribution board itself to be rated for the total connected load without any diversity at all.
Do diversity allowances differ by type of building?
Substantially. The On-Site Guide gives three columns — individual households, small shops and offices, and small hotels and guest houses — and the same load schedule can give very different answers in each. A domestic cooker is banded down heavily; the same cooker in a small shop is barely reduced at all. Choosing the wrong column costs more than choosing the wrong method, and the guide gives no column at all for blocks of dwellings, large hotels or industrial premises.
Can I apply diversity when sizing a distribution board?
Not to the board itself. Regulation 536.4.202 gives three routes to protecting an assembly against overload, and one of them is that the total connected load without diversity does not exceed the rated current of the assembly (InA) and any outgoing unit (Inc). The same regulation states that diversity shall not be used as a means of load curtailment, load control or overload protection. You may use diversity to size an RCCB or switch (Reg 536.4.3.2), and to size the supply — not to make the board smaller.
Do EV charge points get diversity?
Not as an assumption. Section 722 replaces diversity with load curtailment: Regulation 722.311.201 permits load curtailment — load reduction or disconnection, automatic or manual — to be taken into account when determining maximum demand. Read together with Regulation 536.4.202, which forbids diversity being used as a means of load curtailment, "they will not all charge at once" is not available as a design argument. You need an actual load-management system, not an assumption.
What about heat pumps?
BS 7671:2018+A4:2026 does not mention heat pumps at all — not in a section, a regulation, a note or the index. There is therefore no published diversity guidance for them in the standard, and the On-Site Guide's table predates their widespread use. A heat pump is a long-duration, thermostatically controlled load, so the nearest analogous On-Site Guide row is the one that allows no diversity. Treat it as close to continuous unless you have manufacturer data saying otherwise.
What is ADMD?
After Diversity Maximum Demand — the figure a distribution network operator uses for a whole group of dwellings, expressed as kW or kVA per property. It is a different quantity from the diversity you apply inside one installation: ADMD diversifies across many households whose peaks fall at different times, and it gets smaller the more properties you connect. Do not use an ADMD figure to size one property's tails, or an installation diversity to size a network.
Is the switchgear "rated diversity factor" the same thing?
No, despite the name. BS EN 61439 defines the rated diversity factor as the per unit value of the rated current, assigned by the assembly manufacturer, to which outgoing circuits can be continuously and simultaneously loaded taking into account the mutual thermal influences. It is a thermal limit on the enclosure — how much can be drawn at once before it overheats — declared by the manufacturer, not a statement about whether the loads will run together. Conflating it with load diversity is a real and common error.
Sources and verification. BS 7671:2018+A4:2026 Regulations 311.1 (maximum
demand and diversity), 132.1 and 132.3 (design and nature of demand), 132.16 (additions and
alterations), 313.1(e) (suitability of the supply), 433.1.204 and Appendix 15 (standard circuit
arrangements, informative), 523.9, 536.4.3.2 and 536.4.202 (assemblies), 551.7.2.2 (parallel
generation) and 722.311.201 (EV load curtailment); Part 2 definitions of diversity, design
current, load curtailment and load shedding. Diversity allowances are IET On-Site Guide
Appendix A, Tables A1 and A2 — guidance, not the standard, and quoted here in summary rather
than reproduced. The rated diversity factor is BS EN 61439-1 §5.4, with its default values in
BS EN 61439-2 Table 101, which we have not reproduced. Verify every allowance against your own
copies before issue; the numbers on this page are indicative and, as the guide itself notes,
may not align with modern loads.
Work Out the Demand, Then Size the Job
Our free calculator applies the On-Site Guide rules by premises type and shows the working for every category. Or hand the whole assessment over to us and get a load schedule you can defend.